3. Post-Construction Work
After steel sheet pile installation, several follow-up tasks must be carried out. First, the piles must undergo thorough inspection to ensure they meet quality standards. Qualified sheet piles are then lifted and transported to designated locations. Finally, the piles must be properly stacked for future use.
Steel sheet piles must undergo strict inspection regarding both appearance and material quality. These inspections help identify and correct defective piles early, reducing difficulties during pile driving.
During lifting, excessive quantities should not be lifted at once, and special care must be taken to protect the interlocks from damage. Lifting methods vary depending on site needs—either bundled lifting using steel wire ropes or single-piece lifting with specialized equipment.
When stacking sheet piles, the sequence, location, direction, and layout must be planned in advance, taking future construction operations into consideration.